Cutover & Go-Live Plan

Production Migration and Rollout Strategy

Objective

Provide a precise T-30 to T+7 cutover schedule, with go/no-go checkpoints, rollback plan, and smoke-test criteria to guarantee a stable transition from staging to production across all AlShayeb branches (Bethlehem HQ, Ramallah, Jerusalem, Amman, and Egypt).

Quick Launch Checklist

1

Command Center

Establish cutover command center (CFO + PMO + IT Ops) with live war room chat

2

Development Freeze

Freeze development and configuration at T-15

3

Data Migration

Execute final data migration and user access provisioning at T-3

4

Pre-Flight Checks

Verify intercompany balances = 0, all tests passed, and backups complete

5

Go/No-Go Meeting

Conduct Go/No-Go meeting (CFO sign-off mandatory)

6

Hypercare Monitoring

Post-Go-Live monitor system for 7 days; track errors in Helpdesk

7

Rollback Readiness

Implement rollback plan (restore from backup + revert user access) if failure triggers

A. Cutover Timeline – T-30 to T+7 Checklist

Phase / Day Activity Responsible Artifacts / Deliverables Status Gate
T-30 to T-21 Announce go-live date, cutover calendar, and freeze schedule PMO Cutover memo, communication plan ✅ Go-Live prep kickoff
Validate environment capacity (Odoo.sh / DB size, backups) IT Ops Performance report -
T-20 to T-15 Finalize UAT, close all critical defects PMO + QA UAT sign-off sheet ✅ UAT Complete
Train super-users and helpdesk agents HR + AI Dir Training attendance sheet -
T-15 Freeze code and configuration Tech Lead Git tag "Release-1.0" ✅ Code Freeze
T-14 to T-10 Data migration dry run in STAGE Data Gov Lead Migration logs, DQ report -
Validate intercompany reconciliations (pre-go) IC Controller IC report ✅ IC=0
T-9 to T-6 Perform user mapping and access validation IT Ops + HR User access matrix -
Prepare rollback plan & test restore IT Ops DR test report ✅ Backup Verified
T-5 Confirm go/no-go readiness checklist CFO + PMO Pre-Go-Live checklist ✅ Go Decision pending
T-4 Notify all branches of freeze on old systems PMO Comms log -
Lock old databases (readonly) IT Ops Lock confirmation ✅ Data freeze
T-3 to T-2 Perform Final Data Migration to PROD Data Gov Lead Migration logs -
Verify opening balances, HR records, COA Finance Controller Reconciliation doc ✅ Migration validated
T-1 Conduct Go/No-Go meeting CFO + Board Signed Go/No-Go report ✅ Greenlight
T-0 (Go-Live Day) Activate production users IT Ops Access log ✅ Production Live
Monitor first transactions (Finance, HR, AI) PMO Smoke test results ✅ Smoke test pass
T+1 to T+3 Hypercare period; dedicated on-site/remote support PMO + AI Team Daily log -
Monitor performance + IC balance + tickets IT Ops System metrics report ✅ Stable ops
T+4 to T+7 Close hypercare; release post-go-live report PMO + CFO Go-Live summary, lessons learned ✅ Cutover closed

B. Go / No-Go Criteria

Category Go Criteria (Mandatory) No-Go Trigger (Rollback)
Data Integrity Migration success ≥ 99%, DQ score ≥ 98% Major mapping or duplicate errors
Finance Trial balance per branch matches legacy within 0.5% Unreconciled accounts > threshold
Intercompany All IC accounts net to 0 IC imbalance > 0.01
Access / Security User access matrix validated SOD or role violation found
AI Helpdesk ≥90% ticket handling test passed AI responses without citations
Infrastructure Backups verified, RPO ≤ 1 hr Backup failure / restore error
Training / Support Super-user trained at each branch No local support readiness
Stakeholder Approval CFO + PMO sign-off Any sign-off pending

C. Rollback Plan (if No-Go or Critical Failure)

Step Action Responsible Estimated Duration
1 Stop production instance IT Ops Immediate
2 Notify all users, revert to "Read-Only Mode" PMO 15 min
3 Restore backup from pre-cutover (T-1) IT Ops 1–2 hr
4 Validate restoration integrity Tech Lead 1 hr
5 Resume operations in legacy or test environment CFO + PMO 3 hr
6 Investigate failure, document root cause PMO + Audit 24 hr
7 Schedule new cutover window (within 5 days) PMO TBD

Rollback Success Criteria:

  • Data restored to pre-cutover state
  • No financial impact or duplicate entries
  • All audit logs intact and validated

D. Smoke Test Checklist (T-0 to T+1)

Category Test Case Expected Result Pass/Fail Owner
Login & Access User login per branch Success, correct company context - IT Ops
Finance Create and post vendor bill Posted, journal balanced - Finance
Bank reconciliation Statement reconciled - Finance
HR Generate payslip Payslip created; tax calc correct - HR
Projects Create new project + task Saved and visible in dashboard - PMO
AI Helpdesk Submit FAQ AI returns correct article citation - AI Lead
Low confidence → human escalation Escalation ticket created - Curator
Documents Upload and approve contract Saved to correct workspace - PMO
Audit / Logs Verify system log creation Actions recorded in audit log - Audit
Pass Threshold: ≥95% of smoke tests successful within first 24 hours

E. Communication & Escalation Plan

Stage Channel Owner Response Window
Pre-Go-Live Email + Teams announcement PMO 24 hr
Go-Live Day WhatsApp "War Room" + Teams PMO + IT Ops Real-time
Post-Go-Live Daily summary email PMO EOD
Critical Incident Direct call to CFO / Audit IT Ops 15 min

F. Post-Go-Live Stabilization (T+1 to T+7)

Focus Area Task Owner Metric / KPI
System Health Monitor CPU, DB latency, job queue IT Ops Response time < 2s
Helpdesk Volume Track # tickets/day, AI vs manual AI Lead Auto-handled ≥ 70%
Finance Accuracy Validate first journal entries CFO 0 IC imbalance
Audit Compliance Confirm logs intact Audit Dir 100% log coverage
User Adoption Survey end-users HR ≥85% positive feedback
Data Governance Check DQ reports (duplicates, missing) Data Gov Lead <1% invalid records
Training Gaps Capture support trends → new SOPs Edu Dir Weekly report

G. Cutover Documentation Package

Storage Location: /Documents/Cutover/<YYYY-MM-DD>/ and /Audit/Cutover/

Retention: 7 years (audit)

Package Contents:

  • Cutover Calendar & Checklist (PDF)
  • Go/No-Go Approval Record
  • Migration & Validation Logs
  • Smoke Test Results
  • Rollback Plan Verification
  • Post-Go-Live Hypercare Summary
  • CFO & PMO Sign-Off